# Electrical work needed Apr 2026 For room locations see [separate diagram](Power%20Distribution.md#GPO+plan). 1. Heater in Bertrand Russell room - Switchboard circuit breaker \#2A - Currently a wired-in wall-mounted 2kW heater - Convert to plug-in and replace wall connection with GPO, so that we can add a plug-in smart switch 2. GPO for communications equipment - Switchboard circuit breaker \#10B - Currently a quad GPO with another double GPO in parallel in Comms cabinet - Disconnect second dounle GPO - Replace quad GPO with 15A double GPO - If a 2x15A GPO is not allowable, a single would be acceptable. 3. Power supply possibilities for EV charging - We’d like to know what options we have for providing EV charging - Liaise with Glen Bertram for details.